I-70 bridge construction to re-route drivers

Related Story

COLUMBIA - Drivers heading westbound along I-70 will be re-routed to new westbound bridges built along Garth Avenue and Rangeline Street this week.

MoDOT Assistant District Engineer Travis Koestner said, "This week is when we do a pretty major traffic switch."

Starting at 8 p.m. Dec. 8, workers will re-route traffic along Rangeline Street to a new bridge, and starting at 8 p.m. Dec. 9, workers will re-route traffic along Garth Avenue to a new bridge.

The lane shifts will allow the contractor, Emery Sapp and Sons, to tear down the existing eastbound bridges and begin building new ones in their places.

The speed limit on I-70 through the work zone will be reduced from 60 miles per hour to 50 miles per hour. Koestner said the speed reduction could cause major traffic congestion.

"We can't really ask for the cross-state folks to find a different way around. It's Interstate-70. But, if local folks in Columbia could find a different way other than I-70 to get from point A to point B, that would help out tremendously," Koestner said.

The owner of Schaefer Auto body welcomes the construction.

"The roundabout is going to get moved, and I think people will have a better sight line of my business rather than having to pay attention to traffic in that roundabout. So, we're excited." Brett Billington said.

He said he hopes the construction will reduce traffic in the area after workers finish the construction.

"It's definitely much needed and much anticipated," Billington said.

Currently, Emery Sapp and Sons and MoDOT see the projects as ahead of schedule. They said the plan is to complete construction on both directions of I-70 through Columbia by around September 2016.